Market prices

Building material prices in UAE

Market day 9 November 2026 · Dubai · AED

Market prices
ItemSpecification and conditionsUnitVATPrice (AED)Week
Installed works rates
Machine excavation in normal soilBulk or trench excavation by machine in sand or normal soil to about 3 m deep, trimming and stockpiling on site; Dubai subcontract rate per m³, labour and plantm³VAT not stated · Supply and installNo data yet—
Interior wall painting, labour rateInterior wall painting rate per m² of wall, standard repaint; published rate excl. 5% VATFrom the QSM Database, collected from the market on 17 October 2026Source · m²Excl. 5% VAT · Supply and install15—
Backfilling and compactionBackfilling with approved excavated material in 250 mm layers, watered and compacted to 95% MDD; Dubai subcontract rate per m³, labour and plantm³VAT not stated · Supply and installNo data yet—
Slab formworkFormwork to suspended slab soffits up to 3.5 m high, plywood on steel props, fixing and striking; Dubai subcontract rate per m², labour and formwork materialsm²VAT not stated · Supply and installNo data yet—
Steel fixingCutting, bending and fixing rebar of all diameters to drawings, binding wire included, rebar by others; Dubai subcontract rate per ton, labour onlytonVAT not stated · LabourNo data yet—
Concrete placingPlacing, vibrating and curing ready-mix concrete in foundations, columns and slabs, concrete and pump by others; Dubai subcontract rate per m³, labour onlym³VAT not stated · LabourNo data yet—
Blockwork 200 mm, supply and build200 mm hollow concrete blockwork in cement mortar, blocks, mortar and joint reinforcement included; Dubai subcontract rate per m², supply and buildm²VAT not stated · Supply and installNo data yet—
Internal cement plasterInternal cement–sand plaster 15–20 mm in two coats, mesh at joints and corner beads included; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
External cement plasterExternal cement–sand plaster 20–25 mm in two coats with mesh, beads and grooves, scaffolding excluded; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Floor tiling, labour onlyFixing porcelain or ceramic floor tiles up to 60×60 cm with adhesive, grouting included, tiles and materials by others; Dubai subcontract rate per m², labour onlyFrom the QSM Database, collected from the market on 11 October 2026Source · m²No VAT · Labour55—
Internal emulsion paint systemInternal walls and ceilings: one coat sealer, two coats putty and two coats emulsion (Jotun or National Paints); Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
External paint systemExternal walls: alkali-resistant primer and two coats exterior acrylic emulsion (Jotun or National Paints), scaffolding excluded; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Gypsum board false ceilingSuspended gypsum board ceiling 12.5 mm on galvanised MF frame, joints taped and finished ready for paint; Dubai subcontract rate per m², supply and installFrom the QSM Database, collected from the market on 30 October 2026Source · m²VAT not stated · Supply and install97.50—
Torch-applied membrane waterproofingTorch-applied SBS-modified bitumen membrane 4 mm, one layer on primer, laps sealed, upstands included; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Sand–cement floor screedSand–cement floor screed 50–75 mm, levelled to receive floor finishes; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Mineral fibre tile ceiling 60×60 cmSuspended mineral fibre tile ceiling 600×600 mm on exposed 24 mm T-grid, edge trims included; Dubai subcontract rate per m², supply and installLight fittings, diffusers and access panels excluded.From the QSM Database, collected from the market on 23 October 2026Source · m²VAT not stated · Supply and install75—
Imported fill, placed and compactedApproved imported sweet sand or fill, placed in 250 mm layers and compacted to 95% MDD, material included; Dubai subcontract rate per m³m³VAT not stated · Supply and installNo data yet—
Disposal of surplus materialLoading and carting away surplus excavated material or debris to an approved Dubai Municipality dump, tipping fees included; Dubai subcontract rate per m³m³VAT not stated · Supply and installNo data yet—
Anti-termite soil treatmentPre-construction anti-termite treatment of soil under slabs and foundations with an approved termiticide, warranty certificate included; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Column and wall formworkFormwork to columns and walls, plywood or steel panels, fixing and striking; Dubai subcontract rate per m², labour and formwork materialsm²VAT not stated · Supply and installNo data yet—
Blockwork 150 mm, supply and build150 mm hollow concrete blockwork in cement mortar, blocks, mortar and joint reinforcement included; Dubai subcontract rate per m², supply and buildm²VAT not stated · Supply and installNo data yet—
Blockwork laying, labour onlyLaying concrete blocks 100–200 mm in cement mortar, blocks and mortar materials by others; Dubai subcontract rate per m², labour onlym²VAT not stated · LabourNo data yet—
Cement plastering, labour onlyInternal or external cement–sand plaster in two coats, materials by others; Dubai subcontract rate per m², labour onlym²VAT not stated · LabourNo data yet—
Wall tiling, labour onlyFixing ceramic or porcelain wall tiles with adhesive, grouting and trims included, tiles and materials by others; Dubai subcontract rate per m², labour onlyFrom the QSM Database, collected from the market on 11 October 2026Source · m²VAT not stated · Labour70—
Large-format tiling, labour onlyFixing large-format porcelain tiles 60×120 cm and larger with adhesive and levelling clips, tiles and materials by others; Dubai subcontract rate per m², labour onlyFrom the QSM Database, collected from the market on 11 October 2026Source · m²VAT not stated · Labour77.50−0.6%Source ·
Marble and granite flooring, labour onlyStaleLaying 2 cm marble or granite floor tiles or slabs in mortar or adhesive, stone and materials by others; Dubai subcontract rate per m², labour onlyResidential and small-commercial contractor guide, not a large-project subcontract rate. Polishing not included.From the QSM Database, collected from the market on 24 September 2026Source · m²VAT not stated · Labour160—
Epoxy flooring, supply and applyEpoxy floor coating system on prepared concrete, primer and two coats, about 300–500 microns; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Interlock paving, supply and layInterlocking concrete pavers 60–80 mm on compacted sand bed, joints sanded, kerbs excluded; Dubai subcontract rate per m², supply and laym²VAT not stated · Supply and installNo data yet—
External texture coatingTextured acrylic finish to external walls (Terraco Terracoat type): primer and one texture coat, scaffolding excluded; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Drywall partitionDrywall partition: 70 mm metal studs with one layer of 12.5 mm gypsum board each side, joints finished, insulation excluded; Dubai subcontract rate per m², supply and installm²VAT not stated · Supply and installNo data yet—
Cementitious waterproofingTwo coats of polymer-modified cementitious waterproofing to wet areas, balconies or tanks; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Roof waterproofing and insulation systemInverted roof: screed to falls, 4 mm membrane, 50 mm XPS insulation, geotextile and protection screed or tiles; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Lighting point wiringLighting point: PVC conduit, 1.5 mm² wires from the board, back box and switch, light fitting excluded; Dubai subcontract rate per point, supply and installpointVAT not stated · Supply and installNo data yet—
13 A socket outlet pointSocket point: PVC conduit, 2.5 mm² wires from the board, back box and 13 A switched socket; Dubai subcontract rate per point, supply and installpointVAT not stated · Supply and installNo data yet—
Plumbing point per fixtureWater supply (PPR, hot and cold) and drainage (uPVC) point per sanitary fixture to the nearest riser or stack, fixture excluded; Dubai subcontract rate per point, supply and installpointVAT not stated · Supply and installNo data yet—
Split AC installationInstalling a wall split AC up to 2 TR with up to 3 m copper piping, insulation, drain pipe and outdoor bracket; unit supplied by others; Dubai rate per unitExtra piping about AED 50–100 per metre beyond the standard length.From the QSM Database, collected from the market on 4 October 2026Source · unitVAT not stated · Supply and install700—
GI ductworkRectangular galvanised steel ductwork to SMACNA, 0.6–1.0 mm sheet, fabricated and installed with supports; Dubai subcontract rate per m² of duct surface, supply and installm²VAT not stated · Supply and installNo data yet—
Foundation formworkFormwork to sides of footings, raft edges and grade beams, fixing and striking; Dubai subcontract rate per m², labour and formwork materialsm²VAT not stated · Supply and installNo data yet—
Blockwork 100 mm, supply and build100 mm hollow concrete blockwork in cement mortar, blocks and mortar included; UAE subcontract rate per m², supply and buildm²VAT not stated · Supply and installNo data yet—
Bitumen coating to substructureTwo coats of bitumen-based coating to concrete in contact with soil (footings, neck columns, grade beams); Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Demolition of reinforced concreteBreaking out reinforced concrete with hydraulic breakers, loading and disposal off site included; Dubai subcontract rate per m³m³VAT not stated · Supply and installNo data yet—
Polythene sheet under slabs1000-gauge (0.25 mm) polythene sheet laid under ground slabs with 150 mm laps; Dubai subcontract rate per m², supply and laym²VAT not stated · Supply and installNo data yet—
Gypsum plaster to wallsSingle-coat gypsum plaster to internal blockwork walls, ready for paint; UAE subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Marble floor grinding and polishingGrinding, polishing and crystallising marble floors after installation; Dubai subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Skirting fixing, labour onlyFixing tile, porcelain or marble skirting with adhesive, grouting included, materials by others; Dubai subcontract rate per linear m, labour onlylinear mVAT not stated · LabourNo data yet—
Enamel paint to metal or timberAlkyd enamel to new steelwork: one primer and two finishing coats; UAE subcontract rate per m², supply and applym²VAT not stated · Supply and installNo data yet—
Duct insulation 25 mmClosed-cell elastomeric or fibreglass insulation 25 mm to supply ducts, with foil tape and finishing; Dubai subcontract rate per m², supply and installm²VAT not stated · Supply and installNo data yet—
Pre-insulated panel ductworkPre-insulated panel ductwork, small ducts up to 400 mm, fabricated and installed with supports; UAE subcontract rate per m², supply and installm²VAT not stated · Supply and installNo data yet—
Site hoarding 2.4 mTemporary site hoarding 2.4 m high, GI sheet on steel frame; UAE subcontract rate per linear m, supply and erectlinear mVAT not stated · Supply and installNo data yet—
Removing asphalt paving by mechanical breaker, including cart awayAsphalt pavement, priced per m³ of asphalt (source unit) — Breaking and cart awaym³VAT not stated · Supply and installNo data yet—
Breaking out concrete pavingConcrete pavement, per m²; thickness not stated — Breaking out; cart away not statedm²VAT not stated · Supply and installNo data yet—
Demolition of concrete structure (incl. footings)Demolition of concrete structure, general; the source does not split footings — Demolition; cart away not statedm³VAT not stated · Supply and installNo data yet—
Breaking out mass concrete by hand tools, including cart awayMass (plain) concrete, hand tools — Breaking out and cart awaym³VAT not stated · Supply and installNo data yet—
Breaking out RC slabDemolition of reinforced concrete slab — Breaking out; cart away not statedm³VAT not stated · Supply and installNo data yet—
Disposal of concrete and rubble off site, 30 m³ container, per trip30 m³ roll-on roll-off container for concrete and rubble; about 92 AED per m³ of container — Container hire, haulage and disposal; loading not statedtripVAT not stated · Supply and installNo data yet—
Disposal of concrete and rubble off site, 20 m³ container, per trip20 m³ skip for concrete and rubble; about 94 AED per m³ of container — Container hire, haulage and disposal; loading not statedtripVAT not stated · Supply and installNo data yet—
Dismantling existing steel structureDismantling of steel structure, per ton of steel — Dismantling; cart away and scrap credit not statedtonVAT not stated · LabourNo data yet—
Machine excavation in normal soilUp to about 3 m deep — Labour and plant; disposal and backfill excludedm³VAT not stated · LabourNo data yet—
Roof sandwich panel, install only, including flashings and trimsInstallation labour and plant for roof sandwich panels, any core — Installation including flashings and trims as named; panels by othersm²VAT not stated · LabourNo data yet—
Roof sandwich panel, supply and install, including flashings and trimsRoof sandwich panel system, core and thickness not stated by the source — Panels, flashings, trims and installationm²VAT not stated · Supply and installNo data yet—
Structural steel, fabricate and erect, hot-dip galvanised, simple connectionsHot-rolled structural steel frame, all section weights (no light/medium/heavy split in the source), Dubai/UAE subcontract rate — Supply, fabrication, finish as named and erection; bolts and fixings assumed per source wording; finish paint beyond the named system not includedtonVAT not stated · Supply and installNo data yet—
Structural steel, fabricate and erect, intumescent painted, simple connectionsHot-rolled structural steel frame, all section weights (no light/medium/heavy split in the source), Dubai/UAE subcontract rate — Supply, fabrication, finish as named and erection; bolts and fixings assumed per source wording; finish paint beyond the named system not includedtonVAT not stated · Supply and installNo data yet—
Structural steel, fabricate and erect, shop primed, moment connectionsHot-rolled structural steel frame, all section weights (no light/medium/heavy split in the source), Dubai/UAE subcontract rate — Supply, fabrication, finish as named and erection; bolts and fixings assumed per source wording; finish paint beyond the named system not includedtonVAT not stated · Supply and installNo data yet—
Structural steel, fabricate and erect, shop primed, simple connectionsHot-rolled structural steel frame, all section weights (no light/medium/heavy split in the source), Dubai/UAE subcontract rate — Supply, fabrication, finish as named and erection; bolts and fixings assumed per source wording; finish paint beyond the named system not includedtonVAT not stated · Supply and installNo data yet—
Steel structure for hangar, 25–40 m clear span, per m² covered areaPortal or truss frame, high eaves (10–13 m), clear span 25–40 m — Main steel frame supplied, fabricated, shop primed and erected; cladding, purlins/girts if cold-formed, doors, foundations and finish paint excludedm²VAT not stated · Supply and installNo data yet—
Steel structure for hangar or aircraft shelter, 60–80 m clear span, per m² covered areaLong-span truss roof on columns, clear span 60–80 m — Main steel frame supplied, fabricated, shop primed and erected; cladding, purlins/girts if cold-formed, doors, foundations and finish paint excludedm²VAT not stated · Supply and installNo data yet—
Steel structure for warehouse, per m² covered areaPortal frame, low eaves (6–8 m), large span about 25–40 m — Main steel frame supplied, fabricated, shop primed and erected; cladding, purlins/girts if cold-formed, doors, foundations and finish paint excludedm²VAT not stated · Supply and installNo data yet—
Underground RC pump-room shell, per m² floor areaInternal 8×4×4 m (32 m²); walls 300 mm, base 400 mm, roof 250 mm, C35/45, rebar 110 kg per m³ of concrete — Excavation, blinding, RC shell with formwork and rebar, external waterproofing, backfill. Excludes access stair, hatches, ventilation, finishes, MEP and pumpsm²VAT not stated · Supply and installNo data yet—
Underground RC water or fire-water tank, about 1000 m³, per m³ net capacityInternal 18×11.5×5.5 m (0.5 m freeboard, net 1035 m³); walls 450 mm, base 550 mm, roof 300 mm, C35/45, rebar 110 kg per m³ of concretem³VAT not stated · Supply and installNo data yet—
Underground RC water or fire-water tank, about 100 m³, per m³ net capacityInternal 6×5×4 m (0.5 m freeboard, net 105 m³); walls 350 mm, base 450 mm, roof 250 mm, C35/45, rebar 110 kg per m³ of concrete — Excavation 3–6 m with cart away, blinding (material), RC base, walls and roof with formwork and rebar, external membrane waterproofing, internal cementitious coating, backfill with imported sand. Excludes dewatering, shoring, ladders, vents, manholes, pipework, testingm³VAT not stated · Supply and installNo data yet—
Underground RC water or fire-water tank, about 250 m³, per m³ net capacityInternal 10×7×4 m (0.5 m freeboard, net 245 m³); walls 350 mm, base 450 mm, roof 250 mm, C35/45, rebar 110 kg per m³ of concrete — Excavation 3–6 m with cart away, blinding (material), RC base, walls and roof with formwork and rebar, external membrane waterproofing, internal cementitious coating, backfill with imported sand. Excludes dewatering, shoring, ladders, vents, manholes, pipework, testingm³VAT not stated · Supply and installNo data yet—
Underground RC water or fire-water tank, about 500 m³, per m³ net capacityInternal 12×9×5 m (0.5 m freeboard, net 486 m³); walls 400 mm, base 500 mm, roof 300 mm, C35/45, rebar 110 kg per m³ of concrete — Excavation 3–6 m with cart away, blinding (material), RC base, walls and roof with formwork and rebar, external membrane waterproofing, internal cementitious coating, backfill with imported sand. Excludes dewatering, shoring, ladders, vents, manholes, pipework, testingm³VAT not stated · Supply and installNo data yet—
Underground RC water or fire-water tank, about 750 m³, per m³ net capacityInternal 15×10×5.5 m (0.5 m freeboard, net 750 m³); walls 450 mm, base 550 mm, roof 300 mm, C35/45, rebar 110 kg per m³ of concretem³VAT not stated · Supply and installNo data yet—

Every price here comes from the QSM Database: a market price on the date shown with it, with the conditions it holds for. The price on your order changes with quantity, supplier, payment terms and delivery point.