Market prices

Building material prices in Egypt

Market day 1 November 2026 · Greater Cairo · EGP

Market prices
ItemSpecification and conditionsUnitVATPrice (EGP)Week
Installed works rates
Gypsum board ceiling, supply and installGypsum board false ceiling, supply and installation incl. labour; price per m² (wide range by design)m²VAT not stated · Supply and installNo data yet—
Pharaonic stone cladding fixing, labour only (cement fixing)Fixing of Pharaonic stone façade cladding with cement mortar, labour only; price per m² of claddingm²VAT not stated · Supply and installNo data yet—
Pharaonic stone cladding, supply and install (cement fixing)Pharaonic stone façade cladding, stone supply plus cement-mortar fixing; price per m² of claddingm²VAT not stated · Supply and installNo data yet—
Mechanical excavationMachine excavation in all soils except rock, incl. loading and moving spoil within the site, equipment included, per m³; Cairo subcontract rate, supply and install (labour and materials)m³VAT not stated · Supply and installNo data yet—
Backfill with excavated soilBackfilling with excavated material in 25 cm layers with watering and compaction, per compacted m³; Cairo subcontract rate, supply and install (labour and materials)m³VAT not stated · Supply and installNo data yet—
RC footings and tie beams, labourFormwork, steel fixing and casting labour for isolated RC footings and tie beams, incl. nails and tie wire, timber by the client, per m³ of concrete; Cairo subcontract rate, labour only (materials by the client)m³VAT not stated · LabourNo data yet—
RC columns, walls and slabs, labourFormwork, steel fixing and casting labour for RC columns, walls, beams and slabs, incl. nails and tie wire, timber by the client, per m³ of concrete; Cairo subcontract rate, labour only (materials by the client)m³VAT not stated · LabourNo data yet—
Steel fixing, labourCutting, bending and fixing reinforcing steel, incl. tie wire, per ton of steel fixed; Cairo subcontract rate, labour only (materials by the client)tonVAT not stated · LabourNo data yet—
Half-brick walls 12 cm, labourBuilding 12 cm walls in cement or clay bricks with cement mortar, all floors, per m²; Cairo subcontract rate, labour only (materials by the client)m²No VAT · LabourNo data yet—
Internal plaster, labourInternal cement plaster: spatter dash, screeds (bo'aj and awtar) and finishing coat, about 2–2.5 cm, per m²; Cairo subcontract rate, labour only (materials by the client)m²No VAT · LabourNo data yet—
Ceramic floor tiling, labourLaying ceramic floor tiles on sand bed and cement mortar, grouting, skirting excluded, per m²; Cairo subcontract rate, labour only (materials by the client)m²No VAT · LabourNo data yet—
Porcelain floor tiling, labourLaying 60×60 porcelain with tile adhesive and levelling clips, grouting, skirting excluded, per m²; Cairo subcontract rate, labour only (materials by the client)m²No VAT · LabourNo data yet—
Ceramic wall tiling, labourFixing ceramic wall tiles in bathrooms and kitchens with adhesive or mortar, grouting, per m²; Cairo subcontract rate, labour only (materials by the client)m²No VAT · LabourNo data yet—
Internal plastic painting, labourSanding, sealer, 2–3 coats of putty and 2 coats of plastic paint on plastered walls and ceilings, per m²; Cairo subcontract rate, labour only (materials by the client)From the QSM Database, collected from the market on 22 October 2026Source · m²No VAT · Labour65—
Internal plastic painting, supply and applySealer, 2–3 coats of putty and 2 coats of plastic paint of a main local brand on walls and ceilings, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Gypsum board ceiling, supply and installSuspended ceiling in white 12.5 mm gypsum board (Knauf or similar) on galvanised frame, joints taped and filled, access panels, paint and cornices excluded, per m²; Cairo subcontract rate, supply and install (labour and materials)From the QSM Database, collected from the market on 1 November 2026Source · m²VAT not stated · Supply and install400—
Bitumen membrane 4 mm, torch-appliedModified bitumen membrane 4 mm (SBS or APP) on primer, torch-applied with laps and upturns, for roofs and basements, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Electrical point, labourChasing, conduit, back box and wiring for one lighting or socket point in a residential unit, per point; Cairo subcontract rate, labour only (materials by the client)pointNo VAT · LabourNo data yet—
Plumbing point, labourWater supply (PPR) and drainage (PVC) connection for one fixture point in a residential unit, per point; Cairo subcontract rate, labour only (materials by the client)pointNo VAT · LabourNo data yet—
Spoil disposal to public tipLoading and hauling surplus spoil to a licensed public tip about 10–12 km away, tip permits included, per m³; Cairo subcontract rate, supply and install (labour and materials)m³VAT not stated · Supply and installNo data yet—
Backfill with clean sandSupplying and backfilling clean sand in 25 cm layers with watering and compaction, per compacted m³; Cairo subcontract rate, supply and install (labour and materials)m³VAT not stated · Supply and installNo data yet—
Compacted crushed-stone replacementSupplying and compacting crushed dolomite in 20–25 cm layers under foundations, per compacted m³; Cairo subcontract rate, supply and install (labour and materials)m³VAT not stated · Supply and installNo data yet—
RC raft foundation, labourFormwork, steel fixing and casting labour for RC raft foundations, incl. nails and tie wire, per m³ of concrete; Cairo subcontract rate, labour only (materials by the client)m³VAT not stated · LabourNo data yet—
Plain concrete footings, labourFormwork and casting labour for plain concrete footings and blinding, incl. nails, per m³; Cairo subcontract rate, labour only (materials by the client)m³VAT not stated · LabourNo data yet—
Concrete casting, labourPlacing, vibrating, levelling and curing ready-mix concrete delivered by pump, per m³; Cairo subcontract rate, labour only (materials by the client)m³VAT not stated · LabourNo data yet—
One-brick walls 25 cm, labourBuilding 25 cm walls in cement or clay bricks with cement mortar, all floors, per m³; Cairo subcontract rate, labour only (materials by the client)m³VAT not stated · LabourNo data yet—
Half-brick walls 12 cm, supply and buildBuilding 12 cm walls in red clay or cement bricks with cement-sand mortar, materials and labour, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
External plaster, labourExternal cement plaster on façades: spatter dash, screeds and finishing coat, scaffolding excluded, per m²; Cairo subcontract rate, labour only (materials by the client)m²VAT not stated · LabourNo data yet—
Internal plaster, supply and applyInternal cement plaster about 2–2.5 cm with sand and cement, materials and labour, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Porcelain flooring, supply and installLocal grade-1 porcelain 60×60 laid with adhesive and grout, materials and labour, skirting excluded, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Marble or granite flooring 2 cm, labourLaying 2 cm marble or granite floor tiles on mortar bed, incl. skirting, per m²; Cairo subcontract rate, labour only (materials by the client)m²VAT not stated · LabourNo data yet—
Marble or granite stairs, labourFixing marble or granite stair treads and risers on mortar, per linear m of step; Cairo subcontract rate, labour only (materials by the client)linear mVAT not stated · LabourNo data yet—
Interlock laying, labourLaying interlock paving on sand bed with jointing sand and plate compaction, per m²; Cairo subcontract rate, labour only (materials by the client)m²VAT not stated · LabourNo data yet—
External painting, labourPreparing and painting façades with exterior acrylic, primer and 2 coats, scaffolding excluded, per m²; Cairo subcontract rate, labour only (materials by the client)m²VAT not stated · LabourNo data yet—
External acrylic painting, supply and applyPrimer and 2 coats of exterior acrylic of a main local brand on plastered façades, scaffolding excluded, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Gypsum board ceiling, labourInstalling gypsum board suspended ceilings on galvanised frame with joint finishing, per m²; Cairo subcontract rate, labour only (materials by the client)From the QSM Database, collected from the market on 1 November 2026Source · m²No VAT · Labour120—
Gypsum board partition 100 mmGypsum board partition on galvanised studs, joints finished, insulation excluded, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Suspended tile ceiling 60×60Mineral fibre or vinyl-faced gypsum tiles 60×60 cm on white T-bar grid, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Cold bitumen coating to foundationsThree coats of cold-applied bitumen paint on footings, tie beams and buried walls, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Cementitious waterproofing for wet areasFlexible cementitious waterproofing on floors and wall upturns of wet areas, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Electrical point, supply and installOne lighting or socket point incl. conduit, El Sewedy wires and back box, switches and sockets excluded, per point; Cairo subcontract rate, supply and install (labour and materials)pointVAT not stated · Supply and installNo data yet—
Plumbing point, supply and installWater supply in PPR and drainage in PVC for one fixture point, incl. fittings and stop valve, sanitary ware excluded, per point; Cairo subcontract rate, supply and install (labour and materials)pointVAT not stated · Supply and installNo data yet—
Manual excavationHand excavation in ordinary soil for trenches and confined areas, spoil placed beside the trench, per m³; Cairo subcontract rate, labour only (materials by the client)m³VAT not stated · LabourNo data yet—
Hollow block walls 20 cm, labourBuilding 20 cm hollow cement block walls with cement mortar, all floors, per m²; Cairo subcontract rate, labour only (materials by the client)m²No VAT · LabourNo data yet—
Cement-sand screed 5 cmFloor levelling screed of cement and sand about 5 cm thick, materials and labour, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Tile skirting, labourCutting and fixing ceramic or porcelain skirting up to 10 cm high, per linear m; Cairo subcontract rate, labour only (materials by the client)linear mNo VAT · LabourNo data yet—
Breaking reinforced concreteMechanical breaking of reinforced concrete, incl. loading and moving debris within the site, per m³; Cairo subcontract rate, supply and install (labour and materials)m³VAT not stated · Supply and installNo data yet—
Demolishing brick wallsDemolishing brick or block walls incl. plaster, loading debris within the site, per m³; Cairo subcontract rate, labour only (materials by the client)m³VAT not stated · LabourNo data yet—
RC ground slab 15 cm, labourFormwork, steel fixing and casting labour for a 15 cm RC ground slab with joints, per m²; Cairo subcontract rate, labour only (materials by the client)m²VAT not stated · LabourNo data yet—
Hoisting bricks up to the 10th floorCarrying and stacking bricks from street level up to the 10th floor, per 1,000 bricks; Cairo subcontract rate, labour only (materials by the client)1,000 bricksVAT not stated · LabourNo data yet—
Hoisting sand up to the 10th floorCarrying sand from street level up to the 10th floor, per m³; Cairo subcontract rate, labour only (materials by the client)m³VAT not stated · LabourNo data yet—
Large-format porcelain tiling, labourLaying 60×120 cm and larger porcelain with adhesive and levelling clips, skirting excluded, per m²; Cairo subcontract rate, labour only (materials by the client)m²VAT not stated · LabourNo data yet—
Marble wall cladding, labourFixing 2 cm marble or granite on walls with mortar and anchors, per m²; Cairo subcontract rate, labour only (materials by the client)m²VAT not stated · LabourNo data yet—
Marble grinding and polishingGrinding, filling and polishing laid marble floors with machines and materials, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Kerb laying, labourSetting precast concrete kerbs on concrete bed with pointing, per linear m; Cairo subcontract rate, labour only (materials by the client)linear mVAT not stated · LabourNo data yet—
Enamel painting on doors and steelPreparing and painting wood doors or steelwork with primer and 2 coats of gloss enamel, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Façade dry-mix finish, labourApplying cementitious dry-mix finish on plastered façades, scaffolding excluded, per m²; Cairo subcontract rate, labour only (materials by the client)m²VAT not stated · LabourNo data yet—
Epoxy floor coatingEpoxy floor system: primer, putty and 2 coats of epoxy paint, grey, incl. surface preparation, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Gypsum cornice, supply and installCast gypsum cornice 10–15 cm fixed with gypsum adhesive and finished, per linear m; Cairo subcontract rate, supply and install (labour and materials)linear mVAT not stated · Supply and installNo data yet—
Membrane waterproofing, labourTorch-applying bitumen membranes with primer, laps and upturns, per m²; Cairo subcontract rate, labour only (materials by the client)m²VAT not stated · LabourNo data yet—
Roof thermal insulationExtruded polystyrene boards 5 cm laid over roof waterproofing with a separation layer, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Foam concrete roof slopeFoam concrete laid to falls on roofs, average 10 cm, incl. mixing plant and foaming agent, per m²; Cairo subcontract rate, supply and install (labour and materials)m²VAT not stated · Supply and installNo data yet—
Fixing sanitary ware, labourInstalling and testing one WC, washbasin, sink or similar fixture with its mixer, per piece; Cairo subcontract rate, labour only (materials by the client)pieceVAT not stated · LabourNo data yet—
Façade scaffolding, erect and dismantleErecting and dismantling steel tube scaffolding on façades, scaffold rental excluded, per m² of façade; Cairo subcontract rate, labour only (materials by the client)m²VAT not stated · LabourNo data yet—
Light steelwork, fabricate and paintLight steelwork from hollow sections and pipes (railings, frames, canopies), fabricated, installed and painted, per kg; Cairo subcontract rate, supply and install (labour and materials)kgVAT not stated · Supply and installNo data yet—
CFA piles 60 cmContinuous flight auger piles 60 cm diameter, incl. concrete and steel fixing labour, rebar supply excluded, per linear m from platform level; Cairo subcontract rate, supply and install (labour and materials)linear mVAT not stated · Supply and installNo data yet—
Corrugated sheet site hoardingSite hoarding 2.5 m high in 0.7 mm corrugated galvanised sheet on steel posts, incl. fixings, per linear m; Cairo subcontract rate, supply and install (labour and materials)linear mVAT not stated · Supply and installNo data yet—
Saw cutting of RC slabs and heavy floors, per linear mDiamond saw cutting of slabs and heavy floors up to 40 cm deep, Cairo and Giza — Cutting only; breaking, debris removal and disposal priced separately by the sellermVAT not stated · Supply and installNo data yet—
Sandwich panel 75–100 mm, core not stated, supply and installPanels 7.5–10 cm for commercial buildings, hangars and warehouses; core type (PU, EPS or rock wool) not stated by the source — Supply and installation as stated by the seller; flashings and VAT not statedm²VAT not stated · Supply and installNo data yet—
Roof sandwich panel, PU core 40 mm, supply and installPU core 40 mm, pre-painted galvanised skins 0.5/0.4 mm, 1 m cover width, fixed to purlins — Panel and fixing labour; flashings, trims, ridge and transport excluded; fire rating not statedm²VAT not stated · Supply and installNo data yet—
Wall sandwich panel, PU core 50 mm, supply and installPU core 50 mm, pre-painted galvanised skins 0.5/0.4 mm, concealed fixing, fixed to girts — Panel and fixing labour; flashings, trims, ridge and transport excluded; fire rating not statedm²VAT not stated · Supply and installNo data yet—
Steel structure for aircraft shelter or hangar, 25–40 m clear span, per m² coveredHangar or aircraft shelter, 45 kg/m² steel (the source's typical hangar figure; it notes weight rises beyond 40–50 m spans) — Primary and secondary steel (frames, purlins, girts, bracing), primed and erected; excludes cladding, foundations, finish paintm² covered plan areaVAT not stated · Supply and installNo data yet—
Structural steel, heavy sections, fabricated, primed and erectedSteel S235 (ST37) heavy sections; shop fabrication, 2 coats red-oxide primer, erection on prepared bases; bolts and base plates in fabrication — Steel with 5% waste, fabrication, erection, 2 coats primer; excludes finish coats, fire protection, anchor bolts cast in concrete, transport beyond CairotVAT not stated · Supply and installNo data yet—
Structural steel, light sections, fabricated, primed and erectedSteel S235 (ST37) light sections; shop fabrication, 2 coats red-oxide primer, erection on prepared bases; bolts and base plates in fabrication — Steel with 5% waste, fabrication, erection, 2 coats primer; excludes finish coats, fire protection, anchor bolts cast in concrete, transport beyond CairotVAT not stated · Supply and installNo data yet—
Structural steel, medium sections, fabricated, primed and erectedSteel S235 (ST37) medium sections; shop fabrication, 2 coats red-oxide primer, erection on prepared bases; bolts and base plates in fabrication — Steel with 5% waste, fabrication, erection, 2 coats primer; excludes finish coats, fire protection, anchor bolts cast in concrete, transport beyond CairotVAT not stated · Supply and installNo data yet—
Steel structure for warehouse, 25–40 m clear span, per m² coveredPortal-frame warehouse or factory, eaves 8–12 m, 30 kg/m² (midpoint of the source's 25–35 kg/m²) — Primary and secondary steel (frames, purlins, girts, bracing), primed and erected; excludes cladding, foundations, finish paintm² covered plan areaVAT not stated · Supply and installNo data yet—
Underground RC pump room shell, per m² of internal floor areaInternal 8×4 m, 4 m clear height, walls 0.25 m, base 0.3 m, roof 0.2 m, ready-mix 350, rebar 100 kg/m³ — Excavation, blinding, RC shell, rebar, formwork, external membrane, backfill; excludes stairs, doors, hatches, pump plinths, MEPm² internal floorVAT not stated · Supply and installNo data yet—
Underground RC water or fire-water tank, 1000 m³ net, per m³ of capacityInternal 20×10 m, water depth 5 m, 0.5 m freeboard; walls 0.4 m, base 0.6 m, roof slab 0.3 m; C35 ready-mix, rebar 110 kg/m³ — Excavation, blinding, RC base/walls/roof, rebar, formwork, external membrane, internal cementitious coating, backfill, one ladder; excludes dewatering, manhole covers, vents, pipework, disposal of surplus soilm³ net capacityVAT not stated · Supply and installNo data yet—
Underground RC water or fire-water tank, 100 m³ net, per m³ of capacityInternal 6.5×5.2 m, water depth 3 m, 0.5 m freeboard; walls 0.3 m, base 0.4 m, roof slab 0.25 m; C35 ready-mix, rebar 110 kg/m³ — Excavation, blinding, RC base/walls/roof, rebar, formwork, external membrane, internal cementitious coating, backfill, one ladder; excludes dewatering, manhole covers, vents, pipework, disposal of surplus soilm³ net capacityVAT not stated · Supply and installNo data yet—
Underground RC water or fire-water tank, 250 m³ net, per m³ of capacityInternal 10×6.25 m, water depth 4 m, 0.5 m freeboard; walls 0.35 m, base 0.5 m, roof slab 0.3 m; C35 ready-mix, rebar 110 kg/m³ — Excavation, blinding, RC base/walls/roof, rebar, formwork, external membrane, internal cementitious coating, backfill, one ladder; excludes dewatering, manhole covers, vents, pipework, disposal of surplus soilm³ net capacityVAT not stated · Supply and installNo data yet—
Underground RC water or fire-water tank, 500 m³ net, per m³ of capacityInternal 12.5×10 m, water depth 4 m, 0.5 m freeboard; walls 0.35 m, base 0.5 m, roof slab 0.3 m; C35 ready-mix, rebar 110 kg/m³ — Excavation, blinding, RC base/walls/roof, rebar, formwork, external membrane, internal cementitious coating, backfill, one ladder; excludes dewatering, manhole covers, vents, pipework, disposal of surplus soilm³ net capacityVAT not stated · Supply and installNo data yet—
Underground RC water or fire-water tank, 750 m³ net, per m³ of capacityInternal 15×10 m, water depth 5 m, 0.5 m freeboard; walls 0.4 m, base 0.6 m, roof slab 0.3 m; C35 ready-mix, rebar 110 kg/m³ — Excavation, blinding, RC base/walls/roof, rebar, formwork, external membrane, internal cementitious coating, backfill, one ladder; excludes dewatering, manhole covers, vents, pipework, disposal of surplus soilm³ net capacityVAT not stated · Supply and installNo data yet—

Every price here comes from the QSM Database: a market price on the date shown with it, with the conditions it holds for. The price on your order changes with quantity, supplier, payment terms and delivery point.